Part 8: Construction of the Centre for Computing and Engineering

SUB-BASEMENT, MAIN PILLARS AND STRONG FLOOR


Jun 2, 2003 8:00 PM
The walls of the sub-basement slowly rise (looking east from the south-end of the lot).

Jun 6, 2003 12:40 PM
The base of the elevator shaft is complete and the main support pillars rise;
the ground is being prepared for the floor to be poured.

Jun 12, 2003 8:04 PM
The re-bars for the strong-floor used for drop-tests by the Civil Engineering Dept.

Jun 18, 2003 12:44 PM
Half of the main support pillars have been completed. The form for the elevator shaft at the front entrance
(at the base of the blue crane) is under construction.

Jun 23, 2003 12:54 PM
Construction of the form for the elevator shaft at the main entrance is completed. The main support pillars advance past the half-way point.


Camera details: 3.2 megapixel Canon S30 SureShot with 3X optical zoom; Av F2.8 - 8.0; Tv 1/1500 - 15 sec; ISO 50 - 800; manual or automatic focus and light-metering capable.

Other Notes: Original photos have a resolution of 1600x1200 pixels. Panoramas are created using Adobe Photoshop to "stitch-together" 2 or more images. Photos taken through the window are Auto-Leveled then brightened.

Photography and Commentary: Luis Fernandes.